Insurance Point of View: Dealing With Damage and Defects on a Construction Project
|
18 December 2024 |
Statutory Limitation Periods Under Singapore’s Security of Payment Act (SOPA): Preparing for 2025
|
18 December 2024 |
Beyond the Standard: The Need for Southeast Asian Delay Analysis Guidelines
|
24 October 2024 |
Design Engineer vs Forensic Engineer vs Expert Witness
|
24 October 2024 |
Be nice to each other, NEC4 and a critical look at the idea of collaboration
|
03 September 2024 |
Collaboration In Practice Under Singapore PSSCOC Option Module E and NEC4
|
03 September 2024 |
HKIAC Launches Updated Arbitration Rules for 2024 (June 2024)
|
23 June 2024 |
Inflation In Construction Projects
|
26 April 2024 |
Singapore High Court Clarifies The Lodgement Period of Adjudication Applications
|
26 April 2024 |
Understanding Prolongation Cost Claims
|
27 February 2024 |
Construction contracts: Practical tips for mitigation and avoidance of disputes
|
27 February 2024 |
AIAC Arbitration Rules 2023: A Summary of Key Changes
|
27 February 2024 |
Book Review of “Law, Practice and Procedure of Adjudication” Written by Datuk Prof. Sundra Rajoo, Leong Hong Kit and Cindy Wong Xien Yee
|
15 December 2023 |
Building for the future – How claims and expert services promote safe, sustainable and profitable construction
|
15 December 2023 |
How to Claim Compensation for Contractor-Owned Idle Plant – Depreciation costs or rental value?
|
15 December 2023 |
Construction Projects (& Contracting), How Would Environmental, Social & Governance (ESG) Line Up?
|
31 October 2023 |
Whither is a Bridge Too Far? Perspectives on Variations and the doctrine of Cardinal Change in Engineering and Construction Contracts
|
31 October 2023 |
Collaborative Contracting in Construction Projects – A new frontier
|
29 August 2023 |
Enforcement of Procedural Timelines in Arbitrations
|
29 August 2023 |
The Magic Lies in the 'M' – EPC and EPCM Contracts
|
26 June 2023 |